Risk Status Monitors

What Is It?

  • Risk Status Monitors keep you informed about your tasks at risk of incompletion, offering clarity on your progress when needed, through continuous task tracking and real-time analysis.

How It Works

  • Risk Status Monitors operate every 15 minutes, keeping a 1-week cycle that spans half a week before and half a week after the current date.

Unique Insights

  • The Risk Status Monitors assess the state of tasks based on their estimated timelines:

    • At Risk: A task is marked as ‘At Risk’ if it should already be ‘In Progress’ but remains in ‘To Do.’

    • At Danger: A task is flagged as ‘At Danger’ when 30% of its estimated time has passed, but it’s still in ‘To Do.’

    • Delayed: A task is considered ‘Delayed’ if it has reached the end of its estimated timeframe, should be ‘Done,’ but remains in ‘To Do.’

  • This feature smartly detects tasks at risk of incompletion and notifies the right people accordingly:

    • If a task is At Risk: Notifies the assignees directly.

    • If a task is At Danger or Delayed: Notifies the task representatives; if none are defined, it notifies the project representatives.

  • Risk Status Monitors can be tailored for each project when creating or updating a project. You can choose to disable the entire monitoring process or turn off just the notifications—allowing the system to continue monitoring and raising flags without alerts.

  • Currently, Risk Status Monitors are configured as a project-specific setting.

  • Risk Status Monitors start off disabled, you have the option to enable them at any time.

  • Access to enable or disable Risk Status Monitors is restricted to Admin roles and above.

How To Use

  • When creating or editing a project simply enable the Risk Status Monitors.